Neighborhood Street Paving Program

Workers Paving Road

Neighborhood Street Paving Program

The City of Concord continues to invest in local neighborhood streets through our Neighborhood Street Paving Program. Since fiscal year 2016, economic conditions have improved to allow the City to be able to refocus paving initiatives to local neighborhood streets after having completed necessary work on major arterial roads. The Neighborhood Street Paving Program is returning the quality of life to local neighborhoods of our community. We hope to accomplish this goal with the rest of the community as the program continues, provided the community continues to commit funds towards this effort. Since neighborhood streets have a life expectancy of 25 to 30 years, the program is predicated on a 30-year paving cycle. View the paving cycle process at the bottom of the page. Streets are scheduled based on priority defined by objective measures such as pavement conditions, frequency of use, and available funding. The recommended capital improvement project for local streets (CIP #78) is made possible based upon continued funding.

FY 2021 Paving

The fiscal year 2021 (July 1, 2020 - June 30, 2021) budget approved by the Mayor and City Council invests $2.2 million in our Neighborhood Street Paving Program. GMI Asphalt LLC has been contracted for paving for this season. This season’s paving program includes pavement reclamation, maintenance shim/overlays, and cold plane overlays.

Work is weather permitting. Streets will be closed to through traffic and emergency vehicles during construction between 7:00 a.m. and 5:00 p.m. Residents who live on the street will have road access to their homes. On-street parking will also be prohibited between 7:00 a.m. and 5:00 p.m.

A tentative schedule of streets approved for paving is listed below:

Work DateStreet NameSection DescriptionWork Description
April - JuneBishopsgate RoadFull LengthReclaim
April - June
Knoll StreetFull LengthReclaim
April - JuneMartin StreetFull LengthReclaim
April - JunePenacook StreetRumford St. to Auburn St.Reclaim
April - JunePerkins StreetFull LengthReclaim
April - JuneWyman StreetFull LengthReclaim
May - JuneLoudon RoadMain St. to Fort Eddy Rd.Cold Plane / Overlay
May - JuneLoudon RoadEverett Arena to Airport Rd.Cold Plane / Overlay
May - JuneMain StreetLoudon Rd. to Pitman St.Cold Plane / Overlay
July - SeptemberAllison StreetFull LengthShim / Overlay
July - SeptemberChase StreetFull LengthShim / Overlay
July - SeptemberClinton StreetPrinceton St. to S. Spring St.Shim / Overlay
July - SeptemberCornell StreetFull LengthShim / Overlay
July - SeptemberCypress StreetFull LengthShim / Overlay
July - SeptemberDartmouth StreetFull LengthShim / Overlay
July - SeptemberHarvard StreetFull LengthShim / Overlay
July - SeptemberJoffre StreetFull LengthReclaim
July - September
Morton StreetFull Length
Shim / Overlay
July - September
North Spring StreetFull Length
Shim / Overlay
July - September
Noyes StreetFull Length
Shim / Overlay
July - September
Princeton StreetFull Length
Shim / Overlay
July - September
Rumford StreetPleasant St. to Albin St.Shim / Overlay
July - September
Springfield StreetFull Length
Shim / Overlay
July - SeptemberWiggin StreetFull LengthReclaim
July - SeptemberYale StreetFull LengthShim / Overlay

*This schedule is tentative and is subject to change. 

Find weekly paving updates in the City Manager’s Newsletter once paving begins. View the latest newsletter on the City’s homepage at www.concordnh.gov.

FY 2022 Paving

The fiscal year 2022 (July 1, 2021 - June 30, 2022) budget will be adopted by the Mayor and City Council in June 2021. Check back for a tentative paving schedule for fiscal year 2022 once the budget is approved.

Granite Curb Cost-Sharing Program

Residents will be invited to participate in a voluntary granite curb cost-sharing program when streets are scheduled for pavement reclamation. Residents are not obligated to participate. Residents and the City will share the cost of the program. The curb cost-sharing program is only available for streets scheduled for reclamation. Each property will be inspected on a case-by-case basis for approval of granite curbing. The City reserves the right to not install granite curbing based upon certain situations, including drainage concerns. If a resident is interested in participating in the program and their area is approved for curbing, their cost must be paid in full prior to installation. Curbing is installed along the entire property line that abuts the street. More information will be provided directly to residents when notified of pavement reclamation.

Paving Cycle Process

A road has a typical life expectancy of 25 to 30 years. Different methods of maintenance and repair are taken throughout a road’s life cycle to make needed repairs. Pavement life is impacted by many factors: traffic volume, vehicle loads (weight), environmental conditions, maintenance, etc. The more a road is maintained, the longer its life cycle will be. The best practice is to carry out the paving process through its life cycle (with the funding available) to get the full value out of the initial investment. A typical life cycle of a road or street is as follows:

1. Pavement Reclamation

Pavement reclamation is the process of rebuilding a road by recycling the existing asphalt. The road is broken up and mixed with the existing base material. The product is compacted to create a stronger base and three inches of new pavement is placed on the new base. The reclamation process includes the lowering of all catch basins and manholes, grinding the road surface to a 1’ depth, grading the road, and putting down a base layer of pavement. Then the existing granite curb will be reset and any new requested curb will be installed. Existing sidewalks will then be repaired or replaced, manholes and catch basins will be reset, and then the final pavement overlay is applied.

2. Crack Filling

About 5-10 years later, as the road starts to depreciate, the road may begin to crack. A more cost-effective way to maintain the lifespan of the road is to fill the cracks with hot asphalt to prevent water from filtering through the road and creating further damage.

3. Shim Overlay

After the reclamation process in about 5-10 years, another inch of asphalt is laid over the existing paved surface. This additional layer strengthens the initial three inches of pavement to extend the life of the road. The shim/overlay process involves putting down a shim course of pavement to get the road back to an even surface, raising manhole and catch basin covers, and then putting down a 1” final overlay of pavement, followed by a 2’ wide gravel shoulder where there isn’t any curbing in place.

4. Cold Plane & Overlay

5-10 years after that, cold plane and overlay can be placed in part of a process to remove paved areas if necessary. The cold planing and overlay process includes asphalt milling to remove parts of the pavement, shimming with a layer of pavement to fill any ruts that may have developed, raising manhole and catch basin covers, and then placing a 1” final overlay of pavement to maintain the strength of the road for the final 10 years of its life cycle. Finally, a 2’ wide gravel shoulder is placed where curbing is not already in place.