CIP91 - FY17 Sewer Replacement
October 20, 2017 Update:
New sewer main installation has been completed on Putney Avenue and the cross country section off of Forest Street. Next week, the contractor will complete final loaming and seeding, as well as other minor punch list items.

September 1, 2017 Update:
On Wednesday, 09/06/17, the contractor will be fine grading Putney Avenue in advance of paving scheduled for Thursday, 09/07/17. Utility structures will be raised on Friday, 09/08/17. Local traffic disruptions only.

August 11, 2017 Update:
New sewer main will be installed near 6 Forest Street. Forest Street, between Liberty and Valley Streets, will be closed for one day when the new main is connected to the existing main. Local traffic only.

August 4, 2017 Update:
On Putney Avenue, the contractor will be relaying sanitary sewer services from the new main to the property lines. Service interruptions will be brief. Video inspection of the new main is scheduled later in the week to ensure the work complies with current standards and will service the street for many years to come. With the cooperation of homeowners at the end of the street, the City will be constructing a "hammer-head" style turnaround.

July 28, 2017 Update:

Next week, the City's contractor, F. L. Merrill Construction, will continue to replace sanitary sewer main and manhole structures on Putney Avenue. As soon as this work is complete, the gravel roadway surface will be graded and paved.


July 21, 2017 Update:

Next week, F.L. Merrill Construction will begin the new sewer installation on Putney Avenue. On Tuesday, they will be tying into the existing manhole on East Side Drive. Traffic will be reduced to alternating one-way between the hours of 7:00 AM and 6:00 PM. Traffic delays are expected. The road will be reclaimed on Thursday, followed by installation of the new sewer main.